Project Human Resources Management PMP Sample Questions

    Share    Project Human Resources Management

1. Develop Human Resource Plan


2. Acquire Project Team


3. Develop Project Team


4. Manage Project Team


These questions are randomly taken from TechFaq360 PMP success kit



Question - 2

All of the following are examples of Develop Project Team EXCEPT:
1.Negotiations
2.Reorganization and rewards
3.Team building activities
4.Training

Correct Answers are : 1
Explanation :
A is the correct answer.

A is the correct answer. Negotiations is part of Acquire Project Team, Others are parts of Develop Project Team. PMBOK Page no 248.



Question - 9

You are newly appointed as a project manager of an ongoing project. You want to see the role, authority, responsibility and competencies of all the resources working in the project. Which of the following document lists all the above information?
1.Scope statement
2.Project Charter
3.Human Resource Plan
4.WBS

Correct Answers are : 3
Explanation :
C is the correct answer.

C is the correct answer. Human Resource Plan lists role, authority, responsibility and competencies of all the resources working in the project. PMBOK Page no 253.



Question - 16

Reporting to a manager is an example of a__________ relationship.
1.Formal
2.Informal
3.Simple
4.None of the above

Correct Answers are : 1
Explanation :
A is the correct answer.

A is the correct answer. Reporting to a manager is a formal relationship that is designed by the organization.