Project Quality Management PMP Sample Questions

Project Quality Management

    Share    1. Plan Quality

2. Perform Quality Assurance

3. Perform Quality Control

These questions are randomly taken from TechFaq360 PMP success kit


Question - 25

You are the project manager for a big size project and quality is top priority for this project. You have devoted so much of the project time for planning. Why?
1.It is mandatory to allocate much time to planning for a project of this size and with this amount of quality
2.Quality is planned into the project and the planning requires time
3.Quality audits are part of the planning time
4.All of the above

Correct Answers are : 2
Explanation :
B is the correct answer.

Quality is planned into the project and the planning requires time.



Question - 26

You are the project manager and you meet with your project team to ensure the project is completed with no deviations from the project requirements.This is part of?
1.Quality Control
2.Quality assurance
3.Plan Quality
4.All of the above

Correct Answers are : 3
Explanation :
C is the correct answer.

Plan Quality should be completed prior to the work beginning and revisited as needed. Plan Quality: Identifying the quality standards that are relevant to the project and determining how to meet them.



Question - 27

You are managing a project. This project must satisfy industry standards in order to be accepted by the customer. You and your team have studied the requirements and have created a plan to implement the deliverables with the level of quality. This process is called ________.
1.Quality Control
2.Quality assurance
3.Plan Quality
4.All of the above

Correct Answers are : 3
Explanation :
C is the correct answer.

Plan Quality: Identifying the quality standards that are relevant to the project and determining how to meet them.



Question - 28

Identifying the quality standards that are relevant to the project and determining how to meet them is called _________.
1.Quality Control
2.Quality Assurance
3.Plan Quality
4.All of the above

Correct Answers are : 3
Explanation :
C is the correct answer.

Plan Quality: Identifying the quality standards that are relevant to the project and determining how to meet them.



Question - 62

Which of the following is NOT an example of Cost of Conformance?
1.Rework
2.Testing
3.Equipment
4.Training

Correct Answers are : 1
Explanation :
A is the correct answer.

Rework is part of Cost of Nonconformance. Others are part of Cost of Conformance. PMBOK Page no 226.