These questions are randomly taken from TechFaq360 PMP success kit
Question - 2
Overtime associated with the execution effort of a project is estimated at 120 hours with probability 0.5, 250 hours with probability 0.6, and 300 hours with probability 0.3. What is the monetary value of the amount of overtime?
1.300 hours
2.670 hours
3.250 hours
4.100 hours
Correct Answers are : 1
Explanation :
A is the correct answer.
The Monetary Value of the amount of overtime is (120 x 0.5) + (250 x 0.6) + (300 x 0.3) = 300 hours.
Question - 5
You are a project manager of a project. You have organized a meeting to plan risk management. Who could be attendees for this meeting?
1.Stakeholders
2.Team members
3.anyone in organization who is responsible to manage risk planning
4.All of the above
Correct Answers are : 4
Explanation :
D is the correct answer.
A meeting to plan the risk management is called Planning Meeting and Analysis. Attendees could be project manager, selected team members, stakeholders, and anyone in organization who is responsible to manage risk planning.
Question - 10
Probabilistic Analysis of a project, probability of achieving cost and time objectives and trends in Quantitative Risk Analysis results are done during _______.
1.Perform Qualitative Risk Analysis
2.Perform Quantitative Risk Analysis
3.Plan Risk Management
4.Identify Risks
Correct Answers are : 2
Explanation :
B is the correct answer.
Probabilistic analysis of a project, probability of achieving cost and time objectives and trends in Quantitative Risk Analysis results are done during Quantitative Risk Analysis.
Question - 38
The risks of financial gain or loss are called _________.
1.Business Risks
2.Financial Risks
3.Organizational Risks
4.Functional Risks
Correct Answers are : 1
Explanation :
A is the correct answer.
Business gains are directly tied to the risk of the financial gains or loss.
Question - 44
You are a project manager of a project. How you determine whether it is better to make a product or buy a product?
1.Decision Tree Analysis
2.ROI Analysis
3.Ishikawa Diagram
4.All of the above
Correct Answers are : 1
Explanation :
A is the correct answer.
A Decision Tree model can separate the pros and cons of buying product versus building product. Ishikawa Diagram shows cause and effect, not pros and cons.
1600+ PMP Questions Fourth(4th) Edition