Project Time Management PMP Sample Questions

    Share    Project Time Management

1. Define Activities


2. Sequence Activities


3. Estimates Activity Resources


4. Estimates Activity Durations


5. Develop Schedule


6. Control Schedule


These questions are randomly taken from TechFaq360 PMP success kit

Question - 1

An activity has an Early Start(ES) of 5 days and Late Start of 16 days.What is activity's float ?
1.11 days
2.21 days
3.5 days
4.16 days

Correct Answers are : 1
Explanation :
A is the correct answer.

A is the correct answer. Activity float = Late Start - Early Start = 16-5 = 11 days



Question - 4

As a project manager of a project , you have just completed Schedule network diagram. What should you do NEXT time management activity?
1.Estimate Activity Resources
2.Sequence Activities
3.Estimate Activity Durations
4.Develop Schedule

Correct Answers are : 1
Explanation :
A is the correct answer.

A is the correct answer. Schedule network diagram is an output of Sequence Activities, NEXT process is Estimate Activity Resources.



Question - 15

You are project manager of a software project. Your team member want to technical change to a activity which will add more time to that activity. What should you do ?
1.Check the activity is in critical path
2.Allow team member to change the activity
3.Report to senior management
4.Ignore change in activities.

Correct Answers are : 1
Explanation :
A is the correct answer.

A is the correct answer. Check the activity is in critical path is the best option.



Question - 32

You are the project manager for the Project. You are decomposing the Define Activities, the final output is ______?
1.Deliverables
2.Work packages
3.Activity list
4.Milestone List

Correct Answers are : 3
Explanation :
C is the correct answer.

C is the correct answer. Activity list - A list of all the activities that will be performed on the project and a description of each.



Question - 33

You are the project manager for the large Project. You are identifying and documenting relationship among the project activities. This process is called ______?
1.Define Activities
2.Sequence Activities
3.Develop Schedule
4.Control Schedule

Correct Answers are : 2
Explanation :
B is the correct answer.

B is the correct answer. Sequence Activities - identifying and documenting relationship among the project activities. PMBOK Page no 167.

1600+ PMP Questions Fourth(4th) Edition



TechFAQ : Your Technology Expert