These questions are randomly taken from TechFaq360 PMP success kit
Question - 1
An activity has an Early Start(ES) of 5 days and Late Start of 16 days.What is activity's float ? 1.11 days 2.21 days 3.5 days 4.16 days
Correct Answers are : 1 Explanation : A is the correct answer.
A is the correct answer.
Activity float = Late Start - Early Start = 16-5 = 11 days
Question - 4
As a project manager of a project , you have just completed Schedule network diagram. What should you do NEXT time management activity? 1.Estimate Activity Resources 2.Sequence Activities 3.Estimate Activity Durations 4.Develop Schedule
Correct Answers are : 1 Explanation : A is the correct answer.
A is the correct answer.
Schedule network diagram is an output of Sequence Activities, NEXT process is Estimate Activity Resources.
Question - 15
You are project manager of a software project. Your team member want to technical change to a activity which will add more time to that activity.
What should you do ? 1.Check the activity is in critical path 2.Allow team member to change the activity 3.Report to senior management 4.Ignore change in activities.
Correct Answers are : 1 Explanation : A is the correct answer.
A is the correct answer.
Check the activity is in critical path is the best option.
Question - 32
You are the project manager for the Project.
You are decomposing the Define Activities, the final output is ______? 1.Deliverables 2.Work packages 3.Activity list 4.Milestone List
Correct Answers are : 3 Explanation : C is the correct answer.
C is the correct answer.
Activity list - A list of all the activities that will be performed on the project and a description of each.
Question - 33
You are the project manager for the large Project.
You are identifying and documenting relationship among the project activities. This process is called ______? 1.Define Activities 2.Sequence Activities 3.Develop Schedule 4.Control Schedule
Correct Answers are : 2 Explanation : B is the correct answer.
B is the correct answer.
Sequence Activities - identifying and documenting relationship among the project activities. PMBOK Page no 167.
1600+ PMP Questions Fourth(4th) Edition
|